Guide · France · Glossary

French procurement glossary.

French tenders use a precise legal vocabulary from the Code de la commande publique. This glossary explains the terms you’ll meet in a notice, a tender file or a rejection letter, with what each means for a bidder.

Updated 4 Oct 20264 min readChecked against the Code de la commande publique, DAJ guidance and the 2025–2026 decrees, current to October 2026

The rules and the market

Term Meaning
Commande publique Public procurement as a whole: public contracts and concessions.
Code de la commande publique (CCP) The French procurement code, in force since 1 April 2019.
Marché public A public contract.
Acheteur / pouvoir adjudicateur / entité adjudicatrice Buyer; a contracting authority; a contracting entity (utilities).
Seuils européens EU thresholds. In 2026: €140,000 (the State), €216,000 (local authorities) and €5,404,000 (works).
Marché sans publicité ni mise en concurrence A contract without advertising or competition. Allowed below €60,000 (supplies and services) or €100,000 (works) in 2026.
DAJ The Ministry of the Economy’s legal directorate, which publishes procurement guidance.

Procedures

Term Meaning
MAPA (marché à procédure adaptée) The adapted procedure below the EU thresholds. The buyer sets the rules and can negotiate.
Procédure formalisée A formal procedure, above the EU thresholds.
Appel d’offres ouvert Open tender: anyone can bid. At least 35 days (30 electronically).
Appel d’offres restreint Restricted tender: candidates apply first, and those selected bid.
Procédure avec négociation Competitive procedure with negotiation.
Dialogue compétitif Competitive dialogue.
Accord-cadre Framework agreement, up to 4 years (8 for utilities). It accounts for 74% of French contract value.
Bon de commande / marché subséquent An order under a framework, or a follow-on contract competed among framework holders.
Système d’acquisition dynamique (SAD) Dynamic purchasing system.
Allotissement / lot Division into lots.
Variante An alternative solution. Allowed by default since the May 2026 simplification law, unless excluded.

Finding and reading tenders

Term Meaning
BOAMP The official bulletin of public contract notices. Free search and alerts.
JOUE / TED The EU’s Official Journal and its online supplement, TED, for above-threshold notices.
JAL (journal d’annonces légales) A legal-notice newspaper, an alternative to BOAMP for mid-sized contracts.
Profil d’acheteur The buyer’s online platform, where you download documents and bid.
PLACE The State’s procurement platform (marches-publics.gouv.fr).
Avis de marché / avis d’appel public à la concurrence Contract notice.
DCE (dossier de consultation des entreprises) The full tender file, free online from €60,000 when a notice is published.
RC (règlement de la consultation) The rules of the consultation: deadlines, criteria, documents to supply.
CCAP / CCTP Special administrative and technical specifications.
BPU / DPGF / DQE Unit-price schedule, lump-sum price breakdown, and estimated quantities schedule.
Mémoire technique Your technical proposal.
DECP The open data on awarded contracts of €40,000 or more, published on data.gouv.fr.

Applying and bidding

Term Meaning
Candidature / offre Your application (capacity and eligibility), and your bid.
DUME France’s version of the European Single Procurement Document, which buyers must accept at any value.
DC1 / DC2 French forms for the application letter and the candidate’s declaration.
DC4 Declaration of a subcontractor, for the buyer’s acceptance.
Attestation de vigilance (URSSAF) Proof of paid social contributions, renewed every 6 months. Required from the winner.
Kbis The French company-register extract. Foreign firms provide the equivalent.
Groupement (conjoint / solidaire) Consortium: each member liable for its own share, or all liable for the whole.
Mandataire The consortium’s lead member, mandatory in both forms.
Sous-traitance Subcontracting. You can’t subcontract the whole contract.
Offre économiquement la plus avantageuse The most economically advantageous tender.
Offre anormalement basse An abnormally low bid, which must be explained.
Signature électronique Usually required only from the winner. It must be advanced with a qualified certificate, or qualified.

After the award

Term Meaning
Lettre de rejet Rejection letter. Losing bidders can ask for the reasons.
Délai de standstill The wait before signing on formal procedures: 11 days electronic, 16 otherwise.
Référé précontractuel An urgent court challenge before the contract is signed.
Recours Tarn-et-Garonne A challenge to the signed contract by a harmed third party, within 2 months.
Avance Advance payment: mandatory over €50,000 and two months, at least 30% for SMEs on State contracts.
Retenue de garantie A retention guarantee, capped at 3% for SMEs with large buyers.
Délai global de paiement Payment deadline: 30 days (State and local authorities), 50 (hospitals), 60 (public enterprises).
Intérêts moratoires / indemnité forfaitaire Late-payment interest (ECB rate + 8 points) and a €40 collection fee.
Chorus Pro The State’s e-invoicing portal, mandatory for invoices to public buyers. Foreign suppliers can register without a SIRET.
SIRET The French establishment number. Not needed to bid.

Questions

What is a MAPA in French procurement?

A marché à procédure adaptée: the adapted procedure French buyers use below the EU thresholds, and for social and specific services at any value. The buyer designs the process, which may include negotiation, as long as it’s proportionate and announced. Just over half of French contracts of €40,000 or more are MAPAs.

What is the DCE?

The dossier de consultation des entreprises: the complete tender file, including the rules of the consultation (RC), the specifications (CCAP and CCTP) and price schedules. From €60,000, when a notice is published, it must be available online free of charge.

What is the difference between a groupement conjoint and solidaire?

Both are consortia. In a groupement solidaire, every member is liable for the whole contract; in a groupement conjoint, each member answers only for its own share, though the lead member (mandataire) may be made jointly liable if the contract says so.