Closed tender · United States · Public tender

HKZ 150 Bar Maintenance

Argonne Natl Lab - DOE Contractor · IL 60439

Argonne Natl Lab - DOE Contractor in the United States invited bids for “HKZ 150 Bar Maintenance”. Bids closed on 8 October 2026, 13:30 CDT. To qualify, bidders need at least one similar completed work, Safety Data Sheets (SDS) and Job Safety Analysis (JSA). Reference: 6-B187-Q-00461-00.

The work

Maintenance work at HKZ 150 Bar

  • Compliance with all applicable environment, safety and health regulations
  • Protection of safety and health of Laboratory, DOE, and contractor personnel
  • Protection of members of the public and protection of the environment

Key facts

Procedure
Solicitation
Published
05 Oct 2026
Reference
6-B187-Q-00461-00

What it takes to qualify

Worth a closer look

  • The contractor shall not commence on-site work under this contract unless and until the contractor receives approval to proceed from the Project Specialist/Technical Representative.
  • The contractor shall indemnify and hold UChicago Argonne, LLC (Laboratory or Argonne), the University of Chicago and the United States Government, and their directors, officers, trustees, agents, servants, and employees, jointly and severally harmless against any loss or damage...
  • The contractor and each of their subcontractors shall have and maintain for the duration of work this contract the following insurance coverage...
  • The contractor and its subcontractors shall take all reasonable precautions in the performance of the work under this contract to protect the safety and health of the Laboratory, U.S. Department of Energy (DOE), and contractor personnel, as well as members of the public, and protection of the environment.

Experience

  • At least 1 similar work — Maintenance work

Certifications and registrations

Safety Data Sheets (SDS)Must be maintained at the job site
Job Safety Analysis (JSA)Must be maintained at the job site

Policy conditions

No reservation, preference or local-content restriction.

Documents to submit

  1. Names and qualifications of Foreperson and alternatesMust be submitted before starting work
  2. Safety Data Sheets (SDS)Must be maintained at the job site
  3. Job Safety Analysis (JSA)Must be maintained at the job site
  4. DOE-designated Worker Protection PosterMust be maintained at the job site
  5. Workers' compensation noticeMust be maintained at the job site
  6. All permits and activity hazard analysis plansMust be maintained at the job site
  7. Laboratory's 'DOE Differing Professional Opinion Process' posterMust be maintained at the job site